PROJECT : ADANA GALLERIA SHOPPING MALL
LOCATION : Fuzuli Avenue, Adana
CLIENT : Summa Turizm Yatırımcılığı A.Ş.
DESCRIPTION : Shopping Mall Complex 636 shops, 2 floors, 1 underground floor, 250 people capacity conference hall, movie-theatre, food court, 800 cars capacity garage with 200 cars underground
TOTAL CONSTRUCTION AREA : 62 000 m2
EXECUTED DURING : 1989 - 1991

PROJECT : INCLINED GUIDE RAIL STRUCTURE OF BATTLE BOATS
LOCATION : Taşkızak Shipyard, İstanbul
CLIENT : Turkish Naval Forces Command of Taşkızak Shipyard and Etimesgut Timber Industry A.Ş. - Ankara
DESCRIPTION : Construction of inclined guide rail structure of battle boats (on shore and off shore) work includes
2 000 m3 excavation
3 500 m pilling
8 500 m3 reinforced concrete
Ground improvement works
TOTAL CONSTRUCTION AREA : 62 000 m2
EXECUTED DURING : February 1997 – January 1998

PROJECT : MERSİN - OVACIK QUARTZITE MINE
LOCATION : Taşucu Ovacık Village, Mersin
DESCRIPTION : Operation of Quartzite Mine to Supply raw material for Glass Factory in Mersin, work includes
Production and transportation (146 km) of 855.772 tons raw material and 413.314 m3 overburden excavation
EXECUTED DURING : 01.01.1996 – 31.01.1999

PROJECT : MERSİN - YAVCA DOLOMITE MINE
LOCATION : Aslanköy Yavca Village, Mersin
DESCRIPTION : Operation of Dolomite Mine to Supply raw material for Glass Factory in Mersin, work includes
Production and transportation (60km) of 62 000 tons/year raw material and 37 000 m3 /year overburden excavation
EXECUTED DURING : 01.01.1996 – 31.01.1999

PROJECT : TİREBOLU – İNKÖY ROAD
LOCATION : Construction of TİREBOLU – İNKÖY ROAD Tirebolu – Giresun
CLIENT : Municipality of TİREBOLU
SCOPE OF WORK : Construction of 11.3 km asphalt paved road
EXECUTED DURING : 1999 - 2001

PROJECT : BURSA –ORHANELİ THERMAL POWER PLANT SUPPLY OF FILTER MATERIAL
LOCATION : Orhaneli Village, Bursa
DESCRIPTION : Supply of filter material for Desulfurization
Facilities of Orhaneli Thermal Power Plant, work includes production and transportation (16 km) 65 000 tons/year
EXECUTED DURING : 1997 – 2003

Other Projects Completed in Turkey

Return to Projects
 
main page
  about tekar
  projects
  staff
  machine park
  affiliates
türkçe
J.F. Kennedy Cad. No:148/1-2-3 06700 Gaziosmanpaşa / Ankara Turkey Tel : + 90 312 467 82 43 Fax : +90 312 467 39 78

Zebuniso Street, No: 45/1 Dushanbe
Tel: + 992.372 25 59 01 FAX: + 992.372 25 59 04